Online Forum for FM-01 LIFTS 
In order to submit a post you must be logged in, have downloaded specification documents for this tender and the tender must not be closed.

The forum has been closed for posting.
RFx Number Status & Type Details Date
FM-01 LIFTS
Closed
Request for Tender
Issued by: Box Hill Institute
UNSPSC: 72100000 - Building and facility maintenance and repair services
opened
Fri, 29 October 2021 4:30 PM
Closed
Wed, 24 November 2021 2:00 PM
29/10/2021 16:30

Posts

Buyer Post #2 - Clarification Question and Response This post is publicly visible

Q. 2  Is Box Hill advising that they are happy for a principal contractor awarded this tender to then sub-contract out specific work to another supplier depending upon the type or model of the lift?

BHI Response: It is very important to BHI that the contractor or contractors successful through this RFT are able to provide all services within the scope of the contract. It will not be acceptable to us for a contracted supplier to decline work which is within the scope of that detailed in this tender. We are not looking for a support model which involves a head contractor contracting out the services which are the basis for this tender.

Posted on 17/11/2021 14:44 by Box Hill Institute

Buyer Post #1 - Clarification Question and Response This post is publicly visible

BHI has received a clarification question in regard to this tender. In the interests of ensuring that all tenderers have access to the same information, the question and BHI's reply are posted here.

Q.1 Is the institute prepared to look at separate contractors for lifts under this tender?

BHI Response: This tender will give BHI the opportunity to consider whether there is benefit to having a single lift maintenance supplier across all of our campuses or if the present style of arrangement with multiple suppliers remains suitable. At the present time, we have not made any decisions beyond a desire to bring all such lift maintenance contracts into the same time cycle.

Posted on 15/11/2021 13:25 by Box Hill Institute